Renovation Progress

This section contains photographs of the work currently being done on the building. After the building is completed and dedicated, this section will be replaced with a virtual tour.


The Fairview City Hall as it appeared in 1911. The Fairview Elementary School (now the Heritage Building) stands in the background.

2021: Before Restoration

Museum board members and Burns Foundation officers
Side view showing exterior damage
Rear view of building

2022: Cleanup Operations

Plenty of junk to remove
Making progress...
All cleaned out - but oh, those ceilings!

2022: Architectural Assessment

Many exterior masonry repairs are needed
Many windows and lintels need replacing
But the floor joists and foundation are in good shape!

2022: Interior Damage Removal

Interior walls and windows prepped for repair
Damaged flooring removed
Ceilings removed and rafters exposed

2023: Exterior Damage Repair

Broken and missing bricks replaced
Old paint removed
Unstable wall sections replaced

2023: Interior Damage Repair

Walls stabilized
Ceilings stabilized
Damaged subfloor replaced

2023: Interior Preparation

New restroom framed
Electric wiring added
Heating/air conditioning installed
Interior bracing walls built
Old windows removed
Drywall installed

2023: Exterior Preparation

Utilities installed
Sidewalks repaired
Pavilion pad installed
Pavilion installed
New windows installed
New sidewalk built

2023: Interior Finish Work

Window frames installed
Crown moldings & chair rails installed
Door frames installed
Painting started
Painting continues
Painting completed
New flooring installed
Lights installed
Ready for furnishing!

History

This picturesque brick and stone structure was built in 1900 with funds collected from community residents. It served as the first Fairview City Hall until 1916, when it was traded to the North Sanpete School District.


The school district connected the building to the newly-constructed junior high school. It was used as a lunchroom and classroom facility. Many Fairview residents have fond memories of attending classes there.


Some time ago the junior high school was demolished. Miraculously, the old city hall building survived the demolition. Concerned Fairview citizens lobbied for the preservation of the historic structure. Most of the damaged stonework was repaired, a new roof was installed, and various plans were made for its use, but still the building sat vacant. However, it remained in surprisingly good condition for its age.


Because the old City Hall building sits on what is now the Fairview Museum campus, it was long the desire of the museum board to incorporate the building into the museum. But lack of funding kept that from happening.


At the end of 2021 a $250,000 grant was provided by the Fritz B.Burns Foundation to restore the old structure and make it part of the museum. Some Burns Foundation board members are family members of former citizens of Fairview who have fond memories of the town. They wanted to do something for the community, and this restoration was the perfect opportunity.


In 2022 the building was evaluated by an architect, plans were drawn up, and work began to clean out, shore up, and repair the structure, making it safe to occupy. It was determined that portions of the exterior brick walls would need to be replaced and a complete interior frame would need to be constructed in order to stabilize the building and bring it up to seismic code.


In early 2023 the exterior brickwork was repaired. The old yellow paint that covered part of the building was removed to restore the original red brick appearance. Window openings that had been added when the structure was part of the junior high school were filled in and crumbling lintels were replaced. Interior framing was done to stabilize the walls and ceiling. The roof was now firmly supported by the new frame rather than the old brick walls. The damaged hardwood flooring was replaced.


With the exterior and interior repairs complete, the museum was able to obtain a permit to go ahead with the electrical, plumbing, and HVAC installation.

By April of 2023 both interior and exterior construction work were well underway. Internal bracing walls were built and anchored to the exterior brick. Drywall was installed over the bracing walls. The sidewalks around the building were repaired and landscaping was planned, including additional sidewalks and a pavilion.


In the summer of 2023 the new sidewalks were built to provide easier access from the road. The pavilion was built. New windows were installed and the interior was prepared for finishing.


Interior finish work began in the fall of 2023. Utilities were hooked up. Crown moldings and chair rails were installed throughout the building. Interior doors were replaced. The walls were painted and new flooring installed, all in colors reminiscent of the early 1900s. Lighting was installed and power connected.


Work remaining to be done as of winter 2023 includes installing the restroom and kitchenette facilities, putting in furniture and artwork, building stairs and a wheelchair ramp connecting to the Horizon Building, and installing the bell in the bell tower.


The building will be furnished to look much as it may have appeared in 1900. It will be decorated with art and historical artifacts from the museum storage areas.


The building is scheduled to become part of the Fairview Museum in 2024, with a grand opening slated for early spring. It will be named in honor of former Fairview residents Elaine Andersen Rawlinson and Joseph Eli Rawlinson.